|
|
|
Reinforced Concrete
... or how we were slurry when it didn't mesh
A contractor tries to cut corners at our expense
Reinforced concrete is a universal material which is
reasonably well-understood in its structure, behaviour and performance.
Placing it is normally just a matter of commonsense and a bit of experience
so the need for a reinforced concrete slab for our outside swimming pool did
not immediately instil fear into us. Perhaps it should have done.
In the days leading up to this pour, our contractor had become more and more
frantic as his cash problem increased (see other pages for more information
on this). Fortunately his workforce are accustomed to his panic attacks so
carried on in their preparations.
The first problem with the reinforced concrete occurred when I asked the
contractor if he had sorted out which premix plant he was going to order the
concrete from and also what the specification of mix was to be used. He
seemed adamant that the way to do it was to mix it all in his small,
electric mixer; not really a viable consideration. He said he had been
quoted €120 per cubic metre by a premix company for delivering it to our
site yet when my wife phoned we were quoted €75 per cubic metre for exactly
the same mix specification.
He was visibly furious at the unspoken suggestion that he had grossly
inflated the price to us and he attacked the concrete company's
representative on his mobile telephone to such an extent that I feared both
he and us would be blacklisted.
The next difficulty occurred when it came to aligning the stanchions for the
swimming pool. To this day I am not sure how he proposed to get these 6
steel columns to stand in line vertically, horizontally and to be to level,
too. I asked his men to lay a 50mm thick 'blinding' concrete layer so that
at least they would have a clean, hard and solid surface to fix these
stanchions to and not just trying to wedge them into soil.
The second problem occurred when he arrived with a load of metal 'stirrups'
so-called because they loosely resemble their namesake. They are used to
separate the top and bottom layers of reinforcement - both of which need at
least 50mm of cover to prevent the corrosion of the steel. Unfortunately he
had forgotten to take into account the blinding concrete we were going to
lay so the feet of the stirrups would need to actually sit on the soil below
the blinding concrete where they would immediately begin to corrode.
The ultimate fiasco was yet to happen.
Because we were concerned over the contractor's solvency, we had agreed a
fixed, lump sum price with him for the slab. As a result, though, we had to
relinquish control over his modus operandi. This gave him the opportunity he
wanted to insist on mixing the concrete using his own labour. When I pointed
out that two operatives was not enough to mix and place 18 cubic metres of
concrete in one day, he assured us that more would be available on the day.
Over the next few days a large pile of cement sacks and ballast arrived
ready for the scheduled pour which was due to commence at 8 am on a Saturday
and continue uninterrupted until it was completely finished.
The Saturday for the reinforced concrete pour came and there was only the
regular two labourers plus himself available - wholly inadequate for the
task at hand. I probably should not have let them begin mixing but, in any
case, within an hour of the pour beginning we had to stop it. The concrete
being poured was awash with water - more of a slurry than a conglomerate.
There was no way that it would have passed a slump test. On top of that, my
wife had noticed that the cement being used was all past its expiry date.
Finally, the cement and ballast was scarcely being 'shown' the mixer before
being tipped into a barrow. Instead of 5 to 7 minutes of mixing, each batch
was getting around one minute.
I was about to condemn it when our contractor produced an electric poker
vibrator. I had previously emphasised how important it was to see that all
the air was vibrated out of the concrete to prevent 'rats nesting' as it is
called. He assured me that this rather small poker was adequate for the
purpose but, in any case, it was rusted solid and refused to work. That was
the final straw for me and I gave the thumbs-down to the whole venture.
With considerable cursing, the slurry was scooped up into wheelbarrows and
loaded on to the lorry belonging to the contractor. The steel was lifted,
too, in order to get to the underlying concrete. It was then wiped clean and
set aside to be reused. Eventually the lorry drove off, dripping
cement-coloured water as it did, to tip the concrete in a yard the
contractor was building.
Several hours later we were left with a rather damp layer of concrete
blinding instead of a rapidly hardening slab of reinforced concrete. My wife
and I were furious that our contractor had tried such a blatant and almost
insulting con on us. He was being paid nearly €2,000 for the supply of the
concrete (just the concrete, not the reinforcement or the labour) and he had
tried to rip us off with a few hundred euros worth of out of date concrete,
some ballast and an excess of our own tap water.
I suppose the only thing to his credit is that he never once subsequently
suggest that we owed him for it - just as well!
Click here to find out how we used premix
concrete to actually get our usable slab of reinforced concrete.
Reinforced Concrete
|

Home
Sitemap
Italy
Umbria
Landscape
House in Umbria
First home
Second home
House restoration
Wildlife
Building
Health
Comuni
Driving Test
Italy news
Food and drink
Galleries
Italy articles
Link to us
Useful links
Feedback
Contact us
|